HW Issue: Unpublished Backboard Is Invalid, AND Missing from the Repo #17

Closed
opened 2021-11-29 09:46:53 -04:00 by ZAdamMac · 1 comment
ZAdamMac commented 2021-11-29 09:46:53 -04:00 (Migrated from github.com)

The designs for the Rear Expansion board are missing from the repo, so there's your first problem.

They are also flawed in the following ways:

  • The footprint for a resistor to the buzzer is missing. I believe this is actually by design but we need to revalidate.
  • the expansion SPI header is at the wrong pitch. It's on the board as 1.1mm but should be 1.5 mm. Yes. That matters.
  • the expansion headers at J1 and J2 are also wrong and need to match the ones used on the buttons daughterboard, which I believe is also 1.5mm. Without this the board cannot be connected to the main dev board, which defeats the point.
  • The corner through-holes are SLIGHTLY misaligned. This may not cause issues with the standoffs but it would be nice to adjust them slightly to be absolutely sure.
The designs for the Rear Expansion board are missing from the repo, so there's your first problem. They are also flawed in the following ways: - The footprint for a resistor to the buzzer is missing. I believe this is actually by design but we need to revalidate. - the expansion SPI header is at the wrong pitch. It's on the board as 1.1mm but should be 1.5 mm. Yes. That matters. - the expansion headers at J1 and J2 are also wrong and need to match the ones used on the buttons daughterboard, which I believe is also 1.5mm. Without this the board cannot be connected to the main dev board, which defeats the point. - The corner through-holes are SLIGHTLY misaligned. This may not cause issues with the standoffs but it would be nice to adjust them slightly to be absolutely sure.
ZAdamMac commented 2021-11-29 22:28:12 -04:00 (Migrated from github.com)

This is fixed in the revision B design of the boards, which are now published.

This is fixed in the revision B design of the boards, which are now published.
Sign in to join this conversation.
No milestone
No project
No assignees
1 participant
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set.

Reference
zadammac/PETI#17
No description provided.